First day begins edging outline of complex and removing turf. Used portion of material to fill and mound low area left behind after removing old boulder wall.
Cold weather and a bit of snow didn’t get in the way of Installing tile around green complex and bunkers. Begin to spread and tamp aggregate to build up and shape surface.
Shaping
Bunkers built
Dug trenches and installed poly and drain tile in bunker floors. Stacked synthetic turf to begin shaping revetted (stacked synthetic turf) bunker walls on front left of green. Finished shaping bull nose bunker on right side of green. Continued building up base and shaping complex.
The final days consist of rolling out and installing pad and turf. Green, fringe and rough are cut and seamed together. Tee boxes are installed and finishing touches complete. Time to enjoy this beautiful golfscape!