Cleared trees, excavated stumps, removed brush and grass, marked green site and began excavating. Installed drainage, laid out geotextile fabric and built and shaped mounding on back and side of green. Began hauling aggregate to shape green complex and started bunker build.
Extremely wet week but battled the elements to complete bunker and continue building up the base.
Week 2
Week 3
Wet and cold weather conditions continued thru the week.Completed build up and shaping of base.
Installed wiring for low voltage lighting, roughed in tee box locations and installed putting green pad.
Continued wet and cold weather.Installed, seamed and infilled turf for green complex.Filled bunker with sand and received materials for tee box construction.
Week 4
Week 5
Still battling cold and wet weather.Finished tee box builds, installed cups and flags,rolled green and added soil and sod around side and back of green.Cleaned up the job site and repaired access damage from road and driveway.Last but not least, we hit a few shots!!